Confirm the instrument-truck supply boundary
Define the selected tools, line and deployment method, depth and load basis, acquisition channels and required output records for the actual well program. The proposed truck configuration should identify its carrier, installed deployment equipment, operator workspace and power arrangement. Ask the supplier to list supported interfaces and limitations instead of assuming universal instrument compatibility from the product name.
External wellhead and pressure-control equipment require their own competent selection and acceptance. Surface separators, flow meters and effluent handling are separate package responsibilities unless explicitly included in the accepted offer. Any required data connection to those systems needs an identified interface and verification plan. Retain that boundary with the purchase, factory evidence and site handover records.
Start with the job decision
Test Well Truck projects succeed when the equipment scope is tied to a defined operating duty: mobile instrument deployment, depth measurement and data acquisition for an accepted well-survey program. A useful project document separates normal duty, maximum credible duty, standby or transient conditions and the physical interfaces available at site. This keeps procurement language connected to field reality.
Record selected tools and line requirements, accepted depth and load conditions, tool measurement and data requirements and external wellsite interface requirements as ranges rather than isolated peak figures. The supplier can then explain how the line-handling and winch arrangement, depth measurement and instrument interfaces, installed power and control arrangement and surface data-acquisition and operator workspace work together across the intended envelope.
Agree the FAT plan before manufacturing is complete
The inspection and test plan should identify hold points, witness points, acceptance criteria, required instruments and records. A FAT is not simply a visual factory visit. It should verify that the manufactured package matches approved documents and that controls and protection functions behave as agreed.
| Review item | What to confirm | Evidence or input |
|---|---|---|
| line-handling and winch arrangement | Accepted tool, line, working duty and installed access | Configuration-specific deployment response |
| depth measurement and instrument interfaces | Measurement basis, instrument compatibility and record identity | Interface schedule and verification evidence |
| installed power and control arrangement | Installed loads, supply conditions and documented functions | Power arrangement and function schedule |
| surface data-acquisition and operator workspace | Required channels, outputs, workspace and service access | Acquisition schedule and installed layout |

Functional tests should follow the operating sequence
Test permissives, startup logic, normal control, alarms, controlled shutdown and emergency shutdown in a sequence that operators can recognize. Simulate relevant low, high and signal-failure conditions. If full-load testing is not practical at the factory, document the limitation and define the site acceptance test that will close it.
Do not release shipment with undocumented gaps
Compile signed test sheets, material and calibration records, final drawings, manuals, spare-parts lists, packing lists and the punch list. Classify open items by whether they prevent shipment, prevent installation or may be closed during commissioning. Photographs help, but they do not replace signed acceptance records.
Keep a usable project record
Maintain one controlled file containing the approved duty sheet, supplier clarifications, drawings, component data, inspection records, test results, deviations, photographs and signed acceptance documents. Record document revisions and the person responsible for each open item. This prevents the operating team from receiving a package whose final configuration differs from the information used during procurement.
The handover set should also identify installed component models, consumables, calibration intervals, recommended spares, preservation requirements and supplier support contacts. Capture baseline operating readings when the unit is accepted. Those records give maintenance personnel a reference for condition changes and allow later modifications to be reviewed against the original design basis.
Before closing the project, confirm that operators can find the startup, normal-operation, controlled-shutdown and emergency procedures relevant to their unit. Training attendance alone is not sufficient; the responsible team should demonstrate the required checks and know which conditions require escalation rather than continued operation.
Codes, standards and project requirements
Confirm the final specification and acceptance plan against the owner’s project standards, local jurisdiction and OSHA oil and gas extraction safety guidance. The applicable project documents govern whenever they are more specific.