Home / Resources / Test Well Truck Factory Acceptance Test Checklist
Quality assurance

Test Well Truck Factory Acceptance Test Checklist

Use this Test Well Truck FAT framework to verify workmanship, controls, protection functions, documentation and agreed performance before shipment.

Published 2026-08-13 · Practical guidance for oilfield project and procurement teams

Start with the job decision

Test Well Truck projects succeed when the equipment scope is tied to a defined operating duty: mobile separation and measurement of oil, gas and water during well cleanup, appraisal and production testing. A useful project document separates normal duty, maximum credible duty, standby or transient conditions and the physical interfaces available at site. This keeps procurement language connected to field reality.

Record expected phase rates, operating pressure and temperature, fluid PVT behavior and sand and H2S risk as ranges rather than isolated peak figures. The supplier can then explain how the two- or three-phase test separator, multiphase metering instruments, choke and pressure-control manifold and sampling and data-acquisition package work together across the intended envelope.

Agree the FAT plan before manufacturing is complete

The inspection and test plan should identify hold points, witness points, acceptance criteria, required instruments and records. A FAT is not simply a visual factory visit. It should verify that the manufactured package matches approved documents and that controls and protection functions behave as agreed.

Review itemWhat to confirmEvidence or input
two- or three-phase test separatorModel, materials, assembly and accessibilityApproved data sheet and inspection record
multiphase metering instrumentsRotation, alignment, leakage and functional responseTest procedure and measured results
choke and pressure-control manifoldCapacity, cleanliness, connections and service accessDrawing review and functional check
sampling and data-acquisition packageI/O, alarms, trips and event recordsCause-and-effect test sheet
Test Well Truck factory acceptance testing and inspection
Record actual results, instrument IDs, open items and responsible closure dates.

Functional tests should follow the operating sequence

Test permissives, startup logic, normal control, alarms, controlled shutdown and emergency shutdown in a sequence that operators can recognize. Simulate relevant low, high and signal-failure conditions. If full-load testing is not practical at the factory, document the limitation and define the site acceptance test that will close it.

Do not release shipment with undocumented gaps

Compile signed test sheets, material and calibration records, final drawings, manuals, spare-parts lists, packing lists and the punch list. Classify open items by whether they prevent shipment, prevent installation or may be closed during commissioning. Photographs help, but they do not replace signed acceptance records.

Keep a usable project record

Maintain one controlled file containing the approved duty sheet, supplier clarifications, drawings, component data, inspection records, test results, deviations, photographs and signed acceptance documents. Record document revisions and the person responsible for each open item. This prevents the operating team from receiving a package whose final configuration differs from the information used during procurement.

The handover set should also identify installed component models, consumables, calibration intervals, recommended spares, preservation requirements and supplier support contacts. Capture baseline operating readings when the unit is accepted. Those records give maintenance personnel a reference for condition changes and allow later modifications to be reviewed against the original design basis.

Before closing the project, confirm that operators can find the startup, normal-operation, controlled-shutdown and emergency procedures relevant to their unit. Training attendance alone is not sufficient; the responsible team should demonstrate the required checks and know which conditions require escalation rather than continued operation.

Codes, standards and project requirements

Confirm the final specification and acceptance plan against the owner’s project standards, local jurisdiction and OSHA oil and gas extraction safety guidance. The applicable project documents govern whenever they are more specific.

Frequently asked questions

What should a Test Well Truck FAT verify?

Verify conformance to approved documents, workmanship, component identity, controls, alarms, trips, records and the agreed functional test scope.

Can site performance testing replace the FAT?

They serve different purposes. The FAT finds manufacturing and logic issues before shipment; the site test verifies the installed package and actual interfaces.